A court hearing over whether construction of a crude oil pipeline in an environmentally fragile Louisiana swamp will continue focused on whether enough would be done to make up for environmental impacts from the project.
An attorney for Bayou Bridge Pipeline LLC told a federal appeals court panel in Houston Monday that it'll be providing "appropriate compensation" by re-establishing forested wetlands elsewhere in the swamp.
A lawyer for environmental groups suing to stop the construction say the project's considerable impacts haven't been taken into full consideration by federal regulators. He asked the panel to not permanently throw out a previous order that had stopped construction.
At least one judge seemed to downplay concerns by environmental groups that the project is "destroying wetlands." A ruling was expected at a later date.